Saturday, 22 June 2019

The Car Park of a Landmark

Hmmm… The last post doesn’t really reflect the actual works we did for the Dubai Canal. Yeah, the Tolerance Bridge and the Canal is all nice and photogenic, but it’s built by another company altogether! So, here’re pictures showing what we actually constructed in the 1.5 months leading up to the opening of the Dubai Canal. The car park.


Paving works on the road in front of Safa Park, on 31 Oct 2016, 10 days before the official opening ceremony of the Dubai Canal – This was the most difficult part, as this road was the ONLY access to the construction sites of a number of other Contractors (like Besix and Wade Adams). It was the only access leading to the Tolerance Bridge’s and Boardwalk’s south side (built by Besix), and vehicles passed through non-stop as all were rushing to complete the works before the Dubai Canal’s grand opening. (And everybody knows that when Dubai declares something, that something is fixed. Deviate and be ready to be blacklisted, or worse…) So, we started paving at friggin 4am, and sent an army of workers to cordon off the road for 2 hours, by force. (Nope, no one is gonna help you. Here, you have to take things into your own hands, or perish…)


This was the car park on Day 1 of my arrival (24 Sep 2016)


We completed it exactly by midday on 8 Nov 2016 (Day 46) – This is a picture of the completed car park taken in July 2017, during Dad’s visit…


One of the biggest challenges was constructing a retaining wall between the canal boardwalk (which is part of Besix’s scope) and our car park. We got the retaining wall design only in October, and there were a horde of obstructions – building foundations, existing live water pipelines and chambers, abandoned underground pipelines… The photo above shows the start of the retaining wall construction works i.e. the start of steel reinforcement fixing for the retaining wall base on 13 Oct 2016 (Day 20). Mind you, at that time, the retaining wall design still hadn’t been finalized. We received the final design on 23 Oct 2016! And the canal, boardwalk, car park and everything was to be completed by 8 Nov 2016


19 Oct 2016 (Day 26) – Retaining wall in full swing (on left), breaking of a receiving pit in progress (middle) …we would have broken this much earlier if we hadn’t broken a large water pipeline, ahem… As you can see, at this time the canal still hasn’t been flooded


8 Nov 2016 (Day 46) – Whew! Just in time. Canal, bridge, wall and boardwalk all done. Workers resting by the retaining wall (right)


This is the road in front of Safa Park (the one shown in the first picture above) – Look at the mess! – Utility works in progress 11 Oct 2016 (Day 18)


Same location, 2 days before official opening. Nearly done, but still a lot of clutter to clear (left). Look at how many workers were involved. We just bloody swarmed it! – 7 Nov 2016 (Day 45)


This was a real thriller, the ramp going down to the boardwalk from Safa Park road – On 6 Nov 2016, 3 days before opening, we still hadn’t friggin cleared the obstructions. Look at all the water chambers in the middle of the proposed road! – Breaking and adjustment of chamber cover levels in progress – 6 Nov 2016 (Day 44)


One day later, almost there! Look at our army of workers! – 7 Nov 2016 (Day 45)


The road in front of the villas – This was a real pain in the neck. There were all sorts of utility lines below the existing road and we had to complete this while causing the least disturbances to the residents (obviously). Yeah, if only that could be done. At the end, we just worked through, enduring the endless complaints. (Yup, I gave my mobile number to all the residents!) – What a mess! – 17 Oct 2016 (Day 24)


Same location, nearly done – 31 Oct 2016 (Day 38)


Look at all the live power cables under the villa road! It was a nightmare to lower them, and the Electricity Authority have strict procedures on working with live cables!


Another part of the villa road, 7 days before official opening. We were waiting for the canal contractor to install a big ass water pump (or was it a ummm… I forgot) before we could fill it up and build the road on top. At this time, we were still waiting – 2 Nov 2016 (Day 40)


Same location, works completed, morning of the day before inauguration – 8 Nov 2016 (Day 46)


This alley was where I used to park my car before the government and consultant suddenly decided to upgrade the alley into a road, …in the last minute! On 3 Nov 2016, 6 days before opening ceremony, we ripped up the whole tiled alley, on an instruction from the office. It was so sudden, the lady residing in the house beside, raised hell for us because she had a party, and suddenly, there was no parking left. We levelled the friggin alley, lowered some cables, placed kerbstones (the alley had no kerbstones, and was a no-through road) and laid new tiles all in 5 days! – Here, workers giving the new road a final sweep – 8 Nov 2016, 7.30am (Day 46)

And that’s the story of how we friggin finished the car park in 1.5 months. I worked straight out for 46 friggin days, 7am to umm… 8pm, lost 4 friggin kg, and destroyed my entire wardrobe of socks (because I walked throughout the day). Tough, but WE NAILED IT!!!

Saturday, 15 June 2019

Building a Landmark


Yours truly by the Dubai Canal, with the Tolerance Bridge at the back, Nov 2016

Since we touched on the Dubai Canal, here’s a look at the canal during the construction phase, where yours truly was involved for the last 1.5 months prior to the official opening.

Mind you, we (CSCEC, the company I work for) did not construct the canal proper. We constructed two vehicular bridges across the canal, converting two major existing roads into bridges, so that the canal can be constructed underneath the raised bridges. The actual canal including the Tolerance Bridge (a pedestrian bridge) was constructed by a company called Besix.

Here’s one of the bridges CSCEC constructed, the Al Wasl Bridge


My job however was not the bridge. It was constructing and finishing the friggin car park below Al Wasl Bridge, which is the main car park for the Dubai Canal (Tolerance Bridge part) and Safa Park. We did it in a record 1.5 months!


Foreman Aksar Ali, my only foreman for the first ummm 2 weeks of my stint. Look at the muck the car park was in on Day 2 of my arrival. Aksar Ali was good but he had to go back to Pakistan due to some unavoidable circumstances… After he left, there was no friggin foreman, and I had to deal directly with operators and workers!?! Only after a week or so later, (with a lot of complaining from yours truly) did some supervisors started joining my team, whew…


The car park taking form – first day of asphalting works on Day 21 of my arrival


The foremen who subsequently joined the car park team – Sajid (left) and Shahid (middle), with a Chinese foremen of another section (…no, don’t remember his name) on top of the Tolerance Bridge on 10 Nov 2016, right after the opening of the Dubai Canal. Dubai Water Canal was officially inaugurated on the evening of 9 Nov 2016

Thinking back, my site was a good site – Where else could we, road construction people, work in the shade? (The bulk of our works were below the bridge!) And we had fantastic views of the canal and the Tolerance Bridge, so much so that people from our head office, consultants, workers, heck, just about anyone involved with the project, would visit our site just for a photograph! Here’re views of how the canal and the Tolerance Bridge took shape.


Dubai Canal – 24 Sep 2016 (Day 1 of my arrival)


Dubai Canal – 7 Oct 2016 (Day 14)


Dubai Canal flooded – 24 Oct 2016 (Day 31)


Dubai Canal opened! - 11 Nov 2016 (2 days after the inauguration)




Tolerance Bridge – close up views


An unnamed pedestrian bridge further upstream from Tolerance Bridge


Al Wasl Bridge after the Dubai Canal inauguration with a still uncompleted pedestrian bridge behind (the twisted white structure)


The twisted foot bridge completed – during Dad’s visit in July 2017


And this was our site office in Business Bay!

That’s all folks!

Sunday, 9 June 2019

The City Never Sleeps


Dubai skyline from the Tolerance Bridge, Dubai Canal

Hmmm, just to be fair to the city where we live, I’m doing a post (or two…?) on Dubai, since I’ve just recently written about Abu Dhabi and Sharjah, and heck! Even Bahrain.

Dubai never sleeps. (Especially so during Ramadan. But this ain’t about the holy month, since Eid has passed, and it’s back to the old hectic days…) But for the night birds and party lovers, there’s another side of Dubai that you …I seldom see. (At this age, I treasure my sleep more than the silly things I used to stay awake for, hehehe…)

Here goes.


Anu and Karishma at the Dubai Water Canal Boardwalk (I don’t even know why some people call it a water canal? Are there any other canals than water canals? Ear canal maybe…) - The arch behind is the Tolerance Bridge


And so, Dubai has a waterfall, …from a friggin bridge! Lighted up in purple! It’s part of the Dubai Canal, and the water curtain can automatically turn off to allow boats to pass thru… (as in this case). Cool, huh?


Anu at City Walk, Dubai


Whoa, what’s that? A metal egg? Wat’s it do? It doesn’t seem like it does anything. The kids were clambering all over trying to ‘activate’ it. City Walk, Dubai, UAE


Palace Hotel Entrance, Downtown Dubai – This was our Diwali outing 2016. I was completing the Dubai Canal Project, and was dead tired, …but decided to take the family out for a spin


Burj Khalifa at night, from the Palace Hotel

And it’s party time!


Al Sahra Desert Resort… compliments of our niece Karishma and the company she used to work for, Tour Dubai. Normally, you’d have to pay a bomb for this, but Tour Dubai’s staff sometimes get discounts, etc. especially during the quieter months. Arranged during Sweety and dad’s visit in the summer of 2017


Yours truly and a falcon, Al Sahra Desert Resort, Dubai


Another trip arranged by niece Karishma, this time a dinner cruise on a super yacht, the Lotus, compliments of the company she works for now, Dutch Oriental, Dubai Marina, Feb 2019


Karishma and Anu are party lovers, sometimes… in Movenpick Hotel, Bur Dubai, Aug 2017


Kari and Anu at the Courtyard Marriott, Green Community


Emaar (the UAE developer of Burj Khalifa and etc) decided to throw a free party for families, an open air theatre. (It’s actually a gimmick, in conjunction with the launch of their new housing development, Dubai Hills). But what the heck, we had some fun haha. Anu, at the Emaar Dubai Hills Estate. "Maybe that metal egg at City Walk (see above) teleports to this technicolour ball?!?"


Emaar Dubai Hills Estate Office

There! Another quick post done. Good night, sleep tight, don’t let the bed bugs bite…

Saturday, 1 June 2019

Eid Greetings from the UAE

Eid Mubarak everyone!


Sheikh Zayed Grand Mosque, Abu Dhabi

Just a wink of an eye, and Ramadan’s coming to an end. Looks like it's back to the hectic days very soon…

Anyway, wishing all a happy and blessed Eid Al Fitr. Selamat Hari Raya Aidilfitri! Wish all travelling, a safe and relaxed journey.

Putting some photos of Abu Dhabi here for the occasion.


Walkways around the central courtyard of the Sheikh Zayed Grand Mosque – June 2017 (it’s only 2 years late ahem)


Sheikh Zayed Grand Mosque at night – this is the ummm let’s see... 3rd or 4th time we visited the mosque (coz it’s just so elegant, …and it’s FREE!!!) Check out this old post


One of the many fountains at the Sheikh Zayed Grand Mosque


Sheikh Zayed Grand Mosque, from the nearby Wahat Al Karama War Memorial


A monument at the Wahat Al Karama War Memorial, Abu Dhabi






Yas Mall, Abu Dhabi – This is where I sometimes come for lunch during my stint working in the Abu Dhabi Airport Project


Anu at Yas Mall, Abu Dhabi


Sheikh Zayed Bridge, Abu Dhabi, UAE

To all those celebrating Eid, don’t be rash, don’t overeat, and have a wonderful time! Alright, signing out till after the Eid holidays. Enjoy!